Whittier/Lyndale bikeway

The City will enhance the bike connections between several neighborhoods in South Minneapolis and downtown.

Key information

Dates

2020 - 2022

Location

Many locations in South Minneapolis and Downtown Minneapolis

Citywide

Project overview

The project will improve existing bikeways on portions of:

  • 1st Avenue South
  • Blaisdell Avenue South
  • 28th Street

Proposed enhancements include:

  • A two-way bikeway with curb and bollard protection
  • Crossing improvements for pedestrians

Schedule

Winter/Spring 2020

Develop project layout and seek input on bikeway design

Summer 2020

Present design to City Council for approval

2021

Construction between 15th St. and 32nd St.

  • We will continue signing and striping work along this stretch into the 2022 construction season as weather permits.
  • We will plant vegetated medians along this stretch in the 2022 construction season.

2022

Construction will continue between 32nd St. and 40th St.

View interactive map

Traffic impacts

We plan to begin work on the Whittier/Lyndale bikeway the week of September 7, 2021, beginning on the north end.

We will close and detour blocks for short periods of time as necessary.

Project design

Planned improvements

The City will be doing construction on 28th St. and Blaisdell Ave. As part of this construction, we will include concrete curbs and pedestrian medians.

On 1st Ave., we will install bollards and other quick-build methods. This way, we can add the improvements and get ready for the upcoming street reconstruction projects on 1st Ave. between Grant St. and Lake St. in 2024. 

Bikeway design schedule

The design for this bikeway has passed through several approvals.

Variance request

Public Works made a variance request on this project.

  • The Transportation & Public Works Committee approved the variance request on December 9, 2020.
  • The full City Council approved the request on December 18, 2020.
  • MnDOT approved the request on January 21, 2021.

Design layout

Public Works submitted a design layout for this project.

  • The Transportation & Public Works Committee approved the layout on January 6, 2021.
  • The full City Council approved the layout on January 15, 2021.
  • Public Works revised construction plans for another City project to align with approved layout. Public Works completed final construction plans in April 2021. The area that changed was Lake St. reconstruction at Blaisdell Ave., which is a part of the 35W reconstruction project.

View the approved layout

Documents

Open House Presentation Aug 2020

Engagement Summary Oct 2020

Existing Conditions

Virtual Open House August 27, 2020

On August 27, 2020, Public Works held a virtual Open House to share information about the Whittier/Lyndale bikeway project which includes portions of 1st Avenue S, 28th Street, and Blaisdell Avenue S. Staff presented on the draft project layout and held a question and answer section from attendees.

Project phase

This project is completed.

Input

Design

In Progress

Complete

Contact us

Ryan Gottsleben

Project Engineer
Public Works

Phone

612-590-4233