Whittier North residential area ADA pedestrian ramp upgrades and resurfacing.
Dates
2024
Location
Area bounded by Franklin Ave W and E, 1st Ave S, 26th St W, and Lyndale Ave S WhittierProject overview
This project is part of the ongoing street maintenance program.
ADA pedestrian ramp upgrades
City staff will upgrade pedestrian ramps to current ADA standards in 2024.
Resurfacing
City staff will resurface the streets in this area in 2024. We replace the top layer of asphalt pavement to extend the life of a street. The new pavement should last at least 10 years.
View the Whittier North Residential Area ADA Pedestrian Ramp Upgrades and Resurfacing Map
CenterPoint Energy
CenterPoint Energy will be performing work ahead of the pavement resurfacing. For details and updates see their project website.
Read more at the CenterPoint Energy, Minneapolis - Whittier Neighborhood website
Schedule
Project schedule:
- Project work completed by the end of October 2024.
- Mill and overlay work begins the week of September 9th, 2024.
- Select curb and gutter replacement work began the week of July 8th, 2024.
- Project staff held an informational meeting on Monday, May 13th, 2024.
Traffic impacts
Roads closed to traffic in intervals during milling and paving for brief periods of time. Roads will remain open during the evenings and nights.
Project phase
This project is complete.