North Loop resurfacing

The City will remove and add a new layer of asphalt along select streets in the North Loop area.

Key information

Dates

2020-2021

Location

1st St. N., 8th Ave. N., 2nd Ave. N., and 4th St. N. streets in the North Loop area

North Loop

Project overview

In this ongoing street maintenance program, we replace the top layer of asphalt pavement. This extends the life of a street between larger reconstructions. The new pavement should last about 10 years.

Schedule

In 2020, we resurfaced part of this project:

  • 4th St. N. from 5th Ave. to 10th Ave. N.
  • 8th Ave. N. from 2nd St. to 1st. St. N.
  • 1st St. N. from 3rd Ave. to 8th Ave. N.

In 2021, we resurfaced the remaining streets:

  • 2nd Ave. N. from Washington Ave. to 1st St. N.
  • 1st St. N. from Hennepin Ave. to 3rd Ave. N.

We replaced some concrete curbs first, followed by asphalt milling and paving.

 View interactive map

Traffic impacts

We'll close the road and detour through-traffic for short periods of time during asphalt milling and paving.

Project phase

This project is complete as of June 3, 2021.

Input

Design

In Progress

Complete

Paved street lined with cars, trees, and an apartment building

1st St. and 8th Ave. project

Learn more about the 1st St. and 8th Ave. part of this project.

Contact us

Hazel Wolf

Supervisor Engineering Technician