Near North Central area ADA pedestrian ramp upgrades and resurfacing

The City will upgrade pedestrian ramps to ADA standards in 2023. The City will replace the pavement surface in 2024.

Key information

Dates

2023 - 2024

Location

Area bounded by Knox Ave North, Plymouth Ave N, Aldrich Ave N, 15th Ave N., and 16th Ave N

Near-North

Project overview

This project is part of the ongoing street maintenance program

ADA pedestrian ramp upgrades

The City upgraded pedestrian ramps to current Americans with Disabilities (ADA) standards.  This work was completed in 2023.

Resurfacing

City staff will resurface the streets in this area in 2024.  We replace the top layer of asphalt pavement to extend the life of a street.  The new pavement should last at least 10 years.

View the Near North Central area ADA Pedestrian Ramp Upgrades and Resurfacing Documents

View Interactive Map

 

CenterPoint Energy

CenterPoint Energy will be performing work ahead of the pavement resurfacing.  For details and updates see their project website.

Read more at the CenterPoint Energy, Minneapolis - Near North Central website

Schedule

Project schedule:

  • Mill and overlay work to begin the week of July 22, 2024.  
  • Select curb and gutter replacement work began the week of June 3, 2024. 

Traffic impacts

The road will be closed to traffic in intervals during milling and paving for periods of time.  Roads will remain open during the evenings and nights. 

Project phase

This project is in progress.

Input

Design

In Progress

Complete

Photo of City staff using machine to lay fresh asphalt on a street (resurfacing)
Photo of City staff using machine to lay fresh asphalt on a street (resurfacing)

Contact us

Hazel Wolf

Supervisor Engineering Technician
Public Works

Phone

612-772-2524