Minnehaha Residential resurfacing
Dates
2023
Location
Minnehaha residential neighborhoods in the vicinity of Minnehaha Ave S. MinnehahaProject overview
In 2023, City staff will resurface the streets in this area. We replace the top layer of asphalt pavement to extend the life of a street. The new pavement should last at least 10 years.
ADA pedestrian ramp upgrades
We will also be upgrading all existing street corners to comply with the Americans with Disabilities Act (ADA). This work will be completed before the resurfacing process begins.
Schedule
- A virtual public hearing was held on Wednesday, February 22nd, 2023.
- Select curb and gutter replacement work to begin the week of May 15th, 2023.
- Mill and Overlay to begin the week of July 24th, 2023.
- Remaining locations will be milled and overlayed the week of October 30th, 2023.
View the Minnehaha Residential Resurfacing project map
CenterPoint Energy
CenterPoint Energy will be performing work ahead of the pavement resurfacing. For details and updates see their project website.
Read more on the CenterPoint Energy, Minneapolis - Minnehaha Residential Paving website
Traffic impacts
Blocks will be intermittently closed to traffic during asphalt milling and paving for brief periods of time.
Project phase
This project is in progress.