Hennepin Ave. S. reconstruction
Dates
2018 - 2025
Location
Hennepin Ave. S. between Lake St. W. and Douglas Ave. East Isles Lowry Hill Lowry Hill EastProject overview
The City will reconstruct Hennepin Ave. between W. Lake St. and Douglas Ave. Construction will be phased over 2-years. Phase 1, from Lake St W to 26th St, was completed in 2024. Phase 2 will be from 26th St to Douglas Ave occurring in 2025.
The project will update Hennepin Avenue to meet the public’s current and future needs. The new, multimodal design improves space for people to: walk, ride transit, bike, and drive. The layout also provides space for enhanced stations of the future METRO E Line.
Construction updates
Latest project news
- Phase 2 Roadway construction is scheduled to start March 31st from 26th St. to Douglas.
- Phase 1 street construction is substantially complete from Lake St to 26th St and open to traffic.
- Within the Phase 1 segment, there will be various activities going on to finish punch list items, landscaping, and irrigation work.
- Phase 2 Utility work from 26th to 24th until early April. Xcel Energy is improving their equipment along the area and will be working on the east side. This work will take place in the east parking lane and the driving lane.
What to expect
- Roadwork and utility work involves use of heavy equipment that will increase noise, vibration, and dust in work areas.
- Traffic lanes will be closed or restricted. These restrictions will vary by block depending on construction activity.
- Cross street lane restrictions will reduce travel lanes to 1-lane at times.
- Parking lanes will be closed during construction.
- Traffic detours and delays in the area
- Business access will remain open during the construction activities.
- Pedestrian detours around work areas will be set up as needed to enable construction. Greater impacts can be expected at intersections where work is occurring.
For more information, please see the links below:
Weekly stakeholder meeting
The Hennepin Ave S weekly stakeholder meeting will not be held
on Friday, July 4th, due to the Independence Day holiday.
Join us at the Hennepin Ave S weekly stakeholder meeting to get an overview of the upcoming construction work. Weekly stakeholder meetings will occur Fridays, April 4, 2025 through the construction season.
- Fridays
- 10:00 a.m.
via Microsoft Teams - Meeting ID: 289 376 573 134
- Passcode: iR93HZ95
- Call In number: +1 612-276-6670
- Phone Conference ID: 522 207 37#
Accessing the weekly stakeholder meeting via your mobile device may require downloading of the Microsoft Teams app to your mobile device.
Help with Microsoft Teams
Anyone can join a Microsoft Teams web meeting. A free software download may be required. The type of download may vary based on how you join the meeting (computer, android device, apple device).
Past meetings
Public meeting #8 - Construction stakeholder meeting
We held a virtual public meeting on March 12, 2024 to provide construction updates, discuss construction impacts, and answer questions and concerns.
Public meeting #7 - Construction stakeholder meeting
We held a virtual public meeting on February 22, 2024 to provide construction updates, discuss construction impacts, and answer questions and concerns.
Public meeting #6 - Construction stakeholder meeting
We held a virtual public meeting on October 19, 2023 to provide construction updates, discuss construction impacts, and answer questions and concerns.
Public meeting #5 - Pre-construction informational meeting
We held a virtual public meeting on August 15, 2023 to share an overview of the construction schedule, discuss construction impacts, and answer questions and concerns.
Hennepin Ave S public meetings – Pre-2023
Project update - June 26, 2025
Project resources
Project documents
- Hennepin Ave. S. Construction & Traffic Most Recent Updates
- Hennepin Ave. S. reconstruction fact sheet
- Hennepin Ave. S. reconstruction crash study (2016-2019)
- Hennepin Ave. S. parking study (2018)
- Hennepin Ave. S. complete streets checklist
- Bus lane pilot findings summary
- Transportation Action Plan
- Vision Zero
- Complete Streets Policy
- Climate Action Plan
Approved design
Project phase
The project is currently in the in progress phase.
Input
Design
In Progress
Complete