East Minnehaha Parkway

The City will remove and replace 105 feet of clay pipe. We'll also replace manholes.

Key information

Dates

2022

Location

Minnehaha Parkway near 37th Ave S

Minnehaha

Project overview

We've determined the following sanitary sewer needs rehabilitation:

Minnehaha Parkway near 37th Ave S

Year installed: 1926

What we'll do

  • Remove 100 feet of 9” clay pipe
  • Bend and replace with 105 feet of 10” pipe
  • Replace manholes

Background

We assess sewer system conditions on a regular basis to:

  • Find infrastructure rehabilitation (rehab) needs
  • Check over the aging sewer system
  • Maintain and improve the system
  • Keep the system reliable
  • Using the condition and risk data, we focus on the sewers with the most rehab needs.

 

View interactive map

 

Traffic impacts

Westbound E Minnehaha Pkwy will be closed during construction at 37th with a traffic detour.

Project phase

This project is complete

Input

Design

In Progress

Complete