Bryant Ave green stormwater infrastructure

Learn more about green infrastructure on Bryant Avenue.

Key information

Dates

2024-2025

Location

Bryant Ave. S. from Lake St. to 50th St. W.

East Harriet Lynnhurst South Uptown

Project overview

We are improving the rain gardens on Bryant Avenue. Last fall, we mowed vegetation and removed sediment and debris. Next, we will remove invasive plants, smooth steep slopes, and install native plants. Learning from other projects, we will use larger potted plants for this restoration. Throughout the growing season, we will water and weed to make sure plants are healthy. When the rain garden basins are complete, they will collect and treat stormwater runoff.

Background

We reconstructed Bryant Avenue between West 50th Street and Lake Street. This was to improve pedestrian safety and create a bicycle connection in the area. It also supports existing and future transit service. We installed green infrastructure to collect and treat stormwater runoff.

See our previous work on Bryant Ave S

Project resources

Read more about the plants we will use

Find nearby rain gardens

Learn more about our policy on boulevard maintenance and responsibility

Project phase

This project is in progress.

Input

Design

In Progress

Complete

Project timeline

June 2025- Sept 2026

Anticipated project completion

City contractor will weed, water, and maintain vegetation for two full growing seasons

June 2025

Community pollinator planting event

Tentative date June 7th. More details will follow.

June 2025

Basins to be planted

April-May 2025

Rain garden restoration work to begin

Garden preparation crews will:

  • Remove weeds and invasive plants
  • Perform minor grading
  • Install garden bypasses (sandbags). Sandbags will remain installed for most of the year until plants have sufficiently rooted.
March/April 2025

Finalize planting plans

Work with contractor to finalize planting plans for each rain garden basin. We will have 15,000 plants going into nearly 100 gardens. 

January 2025

Communication to Residents

Bryant Avenue residents updated on end of season progress and plans for spring work

Read the update to residents 

Winter 2024-2025

Grow plants

Our contractor will grow a selection of native plants in their greenhouse to ensure healthy, successful plants are ready for spring

Fall 2024

Vegetation management

Basins mowed to manage height and prepare for work in spring

View the boulevard maintenance notice 

October 2024

Communication to residents

Bryant Avenue residents informed of upcoming maintenance to rain gardens. 

Read the update to residents

See a door hanger example 

Contact us

Paul Chellsen

Supervising Stormwater Technician III
Surface Water & Sewer
Public Works

Phone

612-673-2406