North Douglas area ADA pedestrian ramp upgrades and resurfacing
Dates
2023 - 2024
Location
Area bounded by Kenwood Parkway, Vineland Place, Lyndale Ave S, Douglas Ave, and Morgan Ave S Lowry HillProgram overview
This project is part of the ongoing street maintenance program.
ADA pedestrian ramp upgrades
The City will upgrade pedestrian ramps to current Americans with Disabilities (ADA) standards. This work was completed in 2023.
Resurfacing
City staff will resurface the streets in this area in 2024. We replace the top layer of asphalt pavement to extend the life of a street. The new pavement should last at least 10 years.
View the North Douglas Residential Resurfacing Map 2024
CenterPoint Energy
CenterPoint Energy will be performing work ahead of the pavement resurfacing.
Schedule
- Project work completed by the end of October 2024.
- Mill and overlay work begins the week of July 8th, 2024.
- Select curb and gutter replacement work began the week of May 28th, 2024.
- Project staff held a virtual pre-public hearing on Tuesday, April 16th, 2024.
- Upgraded pedestrian ramps to current ADA standards in 2023.
Traffic impacts
Roads closed for mill and overlay work. Roads open for overnight traffic.
Project phase
This project is complete.