58th St W, Sunrise Dr. and 60th St resurfacing
Project overview
Public Works staff plan to remove and add a new layer of asphalt on the streets. A bikeway path will be installed as well, see bikeway project link below.
This project is part of an ongoing street maintenance program. We replace the top layer of asphalt pavement, which extends the life of a street between larger reconstructions. The new pavement should last about 10 years.
Schedule
We will mill and overlay 58th St W, Sunrise Drive, and 60th St between Lyndale Ave S and Penn Ave S from July 5th-8th. During this time the road will be closed and detoured.
Recently identified sewer repairs will need to take place at the intersection of 59th St W and Sunrise Drive, and at the intersection of 58th St W and Bryant Ave S. This moved the final paving of this intersection to the week of August 22nd. The rest of this project was paved as planned.
Traffic impacts
Roads will be closed and detoured during construction.
58 St. W and Sunrise Dr bikeway project
Virtual public meeting
Public Works staff held a virtual public meeting Thursday, February 23, 2022 to:
- Provide an overview of the construction schedule
- Discuss construction impacts
- Answer questions and concerns
Project phase
This project is complete.