58th St. E. Resurfacing

The City will remove and add a new layer of asphalt along 58th St. E. from 28th to 34th Ave. S. in south Minneapolis.

Key information

Dates

2022

Location

58th St. E. from 28th Ave. to 34th Ave. S. in south Minneapolis

Wenonah

Project overview

This project is part of an ongoing street maintenance program. We replace the top layer of asphalt pavement, which extends the life of a street between larger reconstructions. The new pavement should last about 10 years.

Schedule

This project is in progress starting the week of April 25, 2022.  Crews will begin by replacing select curb and gutter.  We will mill and overlay the street on May 6th and 7th.  City crews will paint the striping on the road shortly after this is complete

 

View interactive map

Traffic impacts

58th St E between 28th Ave S and 34th Ave S will be closed and detoured May 6th and 7th. The 34th St ramp to Highway 62 will be closed during this time.

Project phase

This project is complete.