54th St. E. and 57th St. E. resurfacing

The City will remove part of the asphalt on these two streets and overlay each street with a new layer of asphalt. The project limits are 54th St. E. from 28th Ave. S. to Hiawatha Ave. and 57th St. E.

Key information

Dates

May and early June of 2021

Location

54th St. E. from 28th Ave. S. to Minnehaha Ave.; 57th St. E. from 28th. Ave. S. to Cedar Ave., in South Minneapolis

Keewaydin Wenonah

Project overview

We resurfaced 54th St. E. from 28th Ave. S. to Hiawatha Ave. and 57th St. E. from 35W to 28th Ave. S.

In this ongoing street maintenance program, we replace the top layer of asphalt pavement to extend the life of a street between larger reconstructions. The new pavement should last about 10 years. 

View interactive map

Traffic impacts

There were short-term closures to through traffic and detours during construction. 

  • 54th St. was closed and detoured June 3-10, 2021. Access the VA Hospital from the east was detoured to Minnehaha Ave.
  • 57th St. was closed and detoured June 8-15, 2021.

Project phase

This project is complete.