Plans and timeline
Our plans for Minnehaha 3000
Timeline
Open house
On October 2, 2024, we hosted an open house.
We shared the results of our community engagement from the past several months.
Present Minnehaha 3000 update
On October 15, 2024, we presented an update on Minnehaha 3000 to the Committee of the Whole.
Community conversations
In August 2024, we hosted five community conversation focus groups.
This included focused conversations hosted for the following:
- Spanish-speaking community
- Somali community
- Neighborhood residents
- Local businesses
- Businesses in the Lake and Minnehaha area
Community engagement
Open House
On June 10, 2024, we hosted an open house. We shared information about the plans for the Minnehaha 3000 building.
Online survey
Starting June 10, 2024, we have opened a survey to the public. We'll use this survey to collect feedback on use for a community-focused space in the building.
Future community events
We will host more community event sessions to gather community input.
Presented Minnehaha 3000 update
On April 8, 2024, we presented an update on Minnehaha 3000 to the Committee of the Whole.
The presentation gave an overview of the:
- Draft concept
- Cleanup plan for the site
- Next steps for community engagement
Community engagement and location chosen
Community engagement and feedback
In April 2023, the City:
- Gathered feedback on 3rd Precinct building location options.
- Hosted five precinct-wide and eight cultural community meetings.
- Collected opinions through an online survey.
In July 2023, our consultant analyzed the feedback and prepared a report.
Location chosen
In November 2023, City leadership chose 2633 Minnehaha Ave as the new Third Precinct building location.
Contact us
Minnehaha 3000 Team
Office of Public Service
Address
Public Service Center
250 S. Fourth St.
Minneapolis, MN 55414