Planning and timeline

Learn about our plans and timeline for the South Minneapolis Community Safety Center.

Building timeline

View our progress towards planning and building the South Minneapolis Community Safety Center.
2026

Safety center opens

Our goal is to open the South Minneapolis Community Safety Center in 2026.

2025

Complete design work

Design work is finished for the safety center.

October 2024

Contract approval

Contract goes to City Council for approval of the architecture and design firm.

September 2024

Phase one services

Phase one services narrowed down.

August 2024

Request for proposal (RFP)

Request for proposal issued for architecture and design firm.

July 2024

Reports and request for information (RFI)

  • We shared the report about what we heard from community members in the spring.
  • Request for information issued.
    • Service providers could tell us how they might provide services in the safety center.
June 2024

Closed on property

We finished buying the property at 2633 Minnehaha Ave.

January - April 2024

Property inspections

The 90-day due diligence period begins.

During this time, the City will perform:

  • Property inspections
  • Environmental testing
  • More actions as needed

The due diligence period ends April 15, 2024.

January 2024

Funding and purchase agreement

  • $10 million in funding towards these efforts became available January 1, 2024.
  • On January 26, we signed the purchase agreement for 2633 Minnehaha Ave property. 
Nov 11, 2023

Property for Safety Center found

  • The Minneapolis City Council gave approval to purchase 2633 Minnehaha Ave.
  • We will use this property for the South Minneapolis Community Safety Center.
  • The Safety Center will have the 3rd Precinct police station. It'll have other community services and resources as well.