4th Ave S Bikeway

Project Type

Bike lanes

Project Limits

4th Ave S between 10th St S and 11th St S

Construction Start Date

Planned for 2014

Contact Information

Simon Blenski, 612-616-7345 or simon.blenski@minneapolismn.gov

Project Details

A segment of 4th Ave S will be resurfaced in 2014. The street reconditioning project allows for a logical time to reconfigure lane striping and implement projects identified in the 2011 Minneapolis Bicycle Master Plan.

Project Layout

4th Ave S Concept (pdf)

Project Updates

May 27, 2014

A project layout has been posted. The concept includes the removal of one southbound travel lane and the installation of a southbound buffered bike lane. There will be no impacts to parking on 4th Ave S or Metro Transit bus operations. This layout was shared with the Minneapolis Bicycle Advisory Committee on May 20. The layout received approval from the Ward 7 office.

The project will be installed following the mill and overlay of 4th Ave S. The resurfacing project is currently scheduled to begin on May 27.

March 31, 2014

Initial scoping has determined that a southbound bike lane can be installed on 4th Ave S with no impacts to parking or Metro Transit operations.

 

Last updated May 27, 2014